Nagpur: As Mahatranco has scheduled maintenance and repair works at 132 KV Mansar Transmission line from12 noon to 1 pm on January 17 that will affect operation at Navegaon Khairi raw water Pumping Station for one hour. Similarly, a shutdown is also being taken on Wednesday from 10 am to 1 pm on 33 KV Godhani WW Feeder that will affect Pench-IV Water Treatment Plant (WTP).
During this period, the following areas under the elevated service reservoir (ESR) in North and South-West Nagpur will face disruption: Nara ESR, Nara NIT ESR, Nari & Jaripatka ESR, Laxmi Nagar New ESR, Dhantoli ESR, Mhalgi Nagar ESR, Srinagar ESR, Nalanda Nagar ESR, Hudkeshwar & Narsala Tapping: Hudkeshwar and Narsala village area, Bokara Village and Godhani Railway, Sakkardara ESR I&II, Sakkardara ESR III.
During this period, there will be no water supply in these affected areas, and water tanker service will also be temporarily unavailable.