Published On : Thu, Jun 20th, 2024

Nagpur residents suffer as flawed concrete roads turn nightmare in residential areas

Advertisement

concrete roads

Nagpur: The Nagpur Municipal Corporation (NMC) has embarked on a project to construct cement concrete roads in various residential areas across the city. However, this initiative has become a significant source of distress for many residents due to its unplanned and haphazard execution.

Improper pavement height:

Advertisement

In numerous locations, the height of the new pavements is above the plinth level of homes. This design flaw has led to severe issues, particularly during heavy rainfall. The heavy rains on Monday, June 17, exacerbated the situation, causing gushing water to enter homes due to the elevated road levels. Residents were left helpless as their houses flooded.

A video clip highlighting the conditions in Sneh Nagar has brought to light the traumatic experiences of its residents. Shatayu Kadwe and Chandrashekhar Bannagare have both spoken about the severe hardships they face due to the unplanned road construction in their area. The ongoing issues have prompted them to demand a reconstruction that adheres to proper planning and standards.

Walking and driving on these newly constructed roads have become daily challenges. The uneven and unplanned construction makes navigation difficult and increases the risk of accidents. The haphazard construction raises the possibility of serious mishaps. The lack of proper planning and execution has made the roads hazardous for both pedestrians and drivers.

In light of the adverse impacts caused by the current construction approach, residents are demanding that the future road constructions should be planned with careful consideration of the existing residential infrastructure to prevent issues such as elevated pavements and waterlogging.

Immediate corrective actions should be taken for the roads already constructed. This includes adjusting pavement heights and ensuring proper drainage systems to prevent flooding during rains. Implementing stricter safety measures during construction to minimize the risk of accidents and mishaps for residents.

The unplanned construction of cement concrete roads by NMC has turned into a nightmare for residents in various parts of Nagpur. Immediate intervention is required to address the flaws in the current construction and to ensure that future projects are executed with better planning and consideration for the well-being of the residents. The demands and concerns of the affected residents need to be addressed promptly to restore normalcy and safety in these residential areas.